AEM performed various engineering and design services for a major
food-processing manufacturer in Georgia that had been receiving fines and
surcharges for its sewer discharge to the local Publicly Owned Treatment
Works. The wastewater from the food facility activities regularly
exceeded discharge standards for 5-Day Biochemical Oxygen Demand
(BOD5), Total Suspended Solids (TSS), Oil & Grease, and pH range (both
low and high).
AEM conducted a first facility audit to reduce pollutant loadings in
facility wastewater. In particular, best management practices were
recommended to reduce wet washing activities of food materials causing
high TSS and BOD5 and to control acid preservative and caustic cleaners
causing large pH fluctuations. The facility audit showed that industrial
wastewater pretreatment would be necessary in order to meet the standards
of 250 mg/L for BOD5, 250 mg/L for TSS, and 100 mg/L for Oil &
Grease.
AEM developed a design for an aerobic wastewater treatment system.
During the design process, variable flow rates were measured during
weekday and weekend operations and sampling was performed to
determine wastewater characteristics for treatment. AEM determined that
aerobic biological treatment was the best alternative and conducted a
successful treatability study on the wastewater prior to full-scale
implementation. As the design was developed, AEM also prepared the
industrial pretreatment permit application for submittal to the Georgia
Environmental Protection Division – Water Protection Branch.
AEM solicited vendor equipment pricing quotes and procured system
equipment. AEM also developed construction specifications for the
general and specialty contractors for the project.
The system design included a lift station to reroute wastewater flow and a
32,000-gallon activated sludge aeration tank to accommodate the highest
pollutant loadings for the plant’s variable flow conditions. The design
also included a clarifier, sludge holding tank, and automated controls to
operate system pumps and equipment.
AEM assisted the general contractor in obtaining a building permit and
provided oversight during all construction phases, especially assembly,
plumbing, and wiring of the treatment equipment. AEM then commenced
startup activities to reroute wastewater flow and seed the aeration tank
with activated sludge. System parameters were monitored and adjusted as
required to optimize system operation. In addition, AEM provided
training and support for facility personnel for the necessary operation and
maintenance requirements for the system.
After startup activities, monitoring data showed that the system effluent
was meeting the required pretreatment standards for BOD5, TSS, Oils &
Grease, and pH.
|